KIN00024645_Exhibit AP6_2 - Emails between Kingspan and the NHBC from February 2015 to June 2015 with the subject _Kingspan Project Query List_.pdf [pdf]
… you could also provide us with an update on the current position in respect of the reports from the March 2015 fire … you could also provide us with an update on the current position in respect of the reports from the March 2015 fire … to your claim(s) Other than disclosure provided for in this statement, we will not pass any data about you to any other …
Published on: 23 June, 2022
KIN00002244_Email correspondence between NHBC and Kingspan regarding use of K15 in facades above 18m..pdf [pdf]
… you could also provide us with an update on the current position in respect of the reports from the March 2015 fire … you could also provide us with an update on the current position in respect of the reports from the March 2015 fire … your claim(s). Other than disclosure provided for in this statement, we will not pass any data about you to any other …
Published on: 23 June, 2022
MAX00000049_Refurbishment and Demolition Asbestos Survey Report by European Asbestos Services of 91 Grenfell Tower_0.pdf [pdf]
… Record Sample Visual Building No No No Floor Room/Location Position Description Approx. Extent Asbestos Type MAT R/A 1 … all samples, by utilising polythene sample bags fixed into position with cloth tape to avoid spillage during … should be carried out to an approved work method statement, which incorporates all the relevant and current …
Published on: 30 July, 2020
ART00008168_Asbestos Survey Report prepared by European Asbestos Services - Report No_ S30902 covering the Refurbishment_Demolition of 91 Grenfell Tower.pdf [pdf]
… Asbestos Services Ltd Executive Summary Floor Room/Location Position Description Ground Lounge Ce11ing Textured coat1ng … all samples, by utilising polythene sample bags fixed into position with cloth tape to avoid spillage during … should be carried out to an approved work method statement, which incorporates all the relevant and current …
Published on: 25 May, 2022
BLARP20000043_Dr_Barbara_Lane_Supplemental_Report_The_proprietary_smoke_ventilation_system_designed_and_commissioned_by_PSB_UK.pdf [pdf]
… 89 5.2 PSB's opening statement … 133 6.9 My final compliance statement regarding the Gilbert Series 54 dampers as … 253 The alternative proposition to deal with protecting a lobby with extended … together with brief reasons/evidence in support of your position. 2. If not dealt with in (1) above, your response …
Published on: 01 June, 2022
MET00080612_TAB_03- Post Audit Report Adair Tower 02_05_15.pdf [pdf]
… Sole Supplier Risk Name TMO Responsible PersonJanice Wray Position TMO Warden Weekend Occupants 100 - 999 100 - 999 … Sole Supplier Risk Name Default Property Responsible Person Position Address Adair Tower Appleford Road LONDON WlO SEA … are only allowed to wo_rk on site and must provide method statements and schedules of work. TMO also has procedures in …
Published on: 11 March, 2022
IWS00002200_Exhibit ED2_107 - Email chain between Edward Daffarn and Janet Edwards regarding the refusal of official recognition of GAG as a Resident Association.pdf [pdf]
… person who only takes the minutes at meetings, or hold the position of membership secretary only. Such posts will be … room hire, postage etc) • Keep an account book • Prepare statements to the committee and for the annual general … to attend the ARB (Area Review Board) • The composition of the committee should aim to reflect the makeup …
Published on: 18 April, 2021
IWS of Gimja Tekie, Flat 202, 23rd Floor - IWS00000992.pdf [pdf]
… 202, 23rd Floor - IWS00000992.pdf Witness Name: Gimja TEK1E Statement No.: 1 Dated: 21 May 2018 THE GRENFELL TOWER … Although, the letter box would sometimes stick in the open position. 68. I would always use the lifts due to my … Although, the letter box would sometimes stick in the open position. 68. I would always use the lifts due to my …
Published on: 14 November, 2018
CLG00035459_December 2012 announcements on changes to the Building Regulations.pdf [pdf]
… unnecessary costs. In addition to this, guidance on Access Statements has been clarified in Approved Document (AD) M to … design based on Eurocodes will be set in a further statement in 2013. Background Building Regulations provide a … Regulations and standards set out in a written ministerial statement details of the deregulatory aspects of the 2013 …
Published on: 01 November, 2022
TMO00870035_TMO document entitled _TMO Health & Safety Quick Reference_ Estate Staff Information Guide..pdf [pdf]
… needed and may also do a site visit to take photographs, statements, measurements, etc. Any remedial action required … times. Signage, where provided, is intact, appropriately positioned and easy to interpret and must not be text only … Detail of any further action considered necessary Name and position of person making the report 67 TM000870035_0015 …
Published on: 03 September, 2021
TMO00870034_TMO document entitled _TMO Health & Safety Quick Reference_ Estate Staff Information Guide..pdf [pdf]
… needed and may also do a site visit to take photographs, statements, measurements, etc. Any remedial action required … times. Signage, where provided, is intact, appropriately positioned and easy to interpret and must not be text only … Detail of any further action considered necessary Name and position of person making the report 66 TM000870034_0015 …
Published on: 03 September, 2021
TMO00870033_TMO document entitled _TMO Health & Safety Quick Reference Estate Staff Information Guide_.pdf [pdf]
… needed and may also do a site visit to take photographs, statements, measurements, etc. Any remedial action required … times. Signage, where provided, is intact, appropriately positioned and easy to interpret and must not be text only … Detail of any further action considered necessary Name and position of person making the report 67 TM000870033_0015 …
Published on: 03 September, 2021
MET00041040_Exhibit JMB_1 to Judith Blakeman's MET statement dated 07.07.2017 - Email chain Between Peter Maddison, Mr Awoderu, Robert Black (Complaints), Joanna Burke (Complaints Manager) and.pdf [pdf]
… MET00041040_Exhibit JMB_1 to Judith Blakeman's MET statement dated 07.07.2017 - Email chain Between Peter … day issues and concerns Why he was suddenly moved from his position remain a mystery to us We demand KCTMO to arrange … day issues and concerns Why he was suddenly moved from his position remain a mystery to us We demand KCTMO to arrange …
Published on: 19 May, 2021
MET00041622_Exhibit JMB_1 to Judith Blakeman's MET statement dated 07.07.2017 - Email chain between Joanne Burke, GTLA & Peter Maddison regarding complaints about the heating and hot water sys.pdf [pdf]
Published on: 19 May, 2021
KIN00008741_Exhibit MJPE_12 - Kooltherm products fire performance review (the date on the first page of this report is incorrect, it should be dated 27 February 2018).pdf [pdf]
… as well as outlining the current fire performance position for the Kingspan Kooltherm K-Range and K100-Range … along the surface of a sample (orientated in the vertical position under opposed flow conditions). The classification … K107, K108, K112. Customers are informed of the following statements from the technical notes provided: A National …
Published on: 09 May, 2021
BSI00000074_BS 476-23_1987 Fire tests on building materials and structures. Part 23_ Methods for determination of the contribution of components to the fire resistance of a structure..pdf [pdf]
… and placed on the upper flange of the beam prior to the positioning of the floor slabs. 5. 2.5.3 For a loadbearing … and placed on the upper flange of the beam prior to the positioning of the floor slabs. Other suitable constructions … the timber used as the lipping material. j) The following statement: A door which has achieved an integrity rating …
Published on: 31 January, 2024
IWS00000469_IWS of Fatima Boujettif & Exhibit FB_1 - walkway resident - Fire & Aftermath.pdf [pdf]
… FB_1 - walkway resident - Fire & Aftermath.pdf Witness Statement of: Fatima Boujettif No. of statement: 1 Exhibits: 1 Date of statement: 17/05/2018 GRENFELL TOWER PUBLIC INQUIRY WITNESS …
Published on: 13 April, 2022
CCL00001498_Studio E, Grenfell Tower.doc Mast climbing proposals.pdf [pdf]
… a 415 volt 3 phase 32 amp 5 pin outlet adjacent to each position. • A l l MCWP equipment wil l be delivered by hiab … to transfer the MCWP equipment in to its' installation position. • The main contractor is responsible for ensuring … health and safety documentation, risk assessments, method statements etc. CCL00001498 0002 CCL00001498/2 LONDON HOIST …
Published on: 10 February, 2021
NHB00001136_Emails between Kingspan and NHBC regarding K15 in facades over 18m and attaching the K15 Project Query list_9.pdf [pdf]
… you could also provide us with an update on the current position in respect of the reports from the March 2015 fire … you could also provide us with an update on the current position in respect of the reports from the March 2015 fire … your claim(s). Other than disclosure provided for in this statement, we will not pass any data about you to any other …
Published on: 08 July, 2022
NHB00001136_Emails between Kingspan and NHBC regarding K15 in facades over 18m and attaching the K15 Project Query list_7.pdf [pdf]
… you could also provide us with an update on the current position in respect of the reports from the March 2015 fire … you could also provide us with an update on the current position in respect of the reports from the March 2015 fire … your claim(s). Other than disclosure provided for in this statement, we will not pass any data about you to any other …
Published on: 08 July, 2022