TMO10049899_Exhibit MA_12 - 22 November 2012 Design Team Meeting no.11 minutes.pdf [pdf]
Published on:
TMO10001231_Appleyards Minutes of Design Team Meeting No 11 that took place on 22 November 2012.pdf [pdf]
… options for differing, more prominent, colours for the cladding. MA noted that feedback during resident … options for differing, more prominent, colours for the cladding. MA noted that feedback during resident …
Published on:
ART00007450_Exhibit SC2_9 - Attachment_ Financial Statement Nr 3 prepared by AUK dd. 4 November 2014.pdf [pdf]
… 88 External Fac;:ade (new wall, Cassette fix aluminium cladding, windows without louvre panel over tile and turn … 88 External Fac;:ade (new wall, Cassette fix aluminium cladding, windows without louvre panel over tile and turn …
Published on:
ART00007412_Exhibit SC2_12 - Attachment_ Financial Statement Nr 4 prepared by AUK dd. 24 November 2014.pdf [pdf]
… 88 External Fac;:ade (new wall, Cassette fix aluminium cladding, windows without louvre panel over tile and turn … 88 External Fac;:ade (new wall, Cassette fix aluminium cladding, windows without louvre panel over tile and turn …
Published on:
MAX00000634_Fordham, Schedule of M&E Surveys, J4614_A(64)502 Rev _®Table 1_ Stage D M&E Surveys and Table 2_ Pre Tender M&E Surveys.pdf [pdf]
… clashes with the demolit ion proposals or the new over cladding. Rubbish Chute Walk route and record location of … clashes with the demolit ion proposals or the new over cladding. Rubbish Chute Walk route and record location of …
Published on:
RBK00029922_2018.09.25 Witness Statement and Index of Ruth Angel (RBKC).pdf [pdf]
… drawing up plans for Grenfell, was considering options for cladding, and was providing castings for the development … of materials on Grenfell or the cost of materials such as cladding. However as I would not have been a key officer for … drawing up plans for Grenfell, was considering options for cladding, and was providing castings for the development …
Published on:
HOM00005582_London_Assembly_report_on_fire_risks_in_London_s_tall_and_timber_framed_buildings.pdf [pdf]
… as internal fire separating walls, protective linings and claddings and fire stopping in cavities are incomplete. Only … as internal fire separation, fire protective linings and claddings and fire stopping barriers within cavities and … as internal fire separation, fire protective linings and claddings and fire stopping barriers within cavities and …
Published on:
INQ00014711_Louise Upton Para 45 - Fire Safety in London, Fire risks in London's Tall and Timber Framed Buildings.pdf [pdf]
… INQ00014711_Louise Upton Para 45 - Fire Safety in London, Fire risks in … include extra statutory fire safety features into specified classes of development such as schools and some categories … include extra statutory fire safety features into specified classes of development such as schools and some categories …
Published on:
HOM00046087_Exhibit NH_5 to the witness statement of Nick Hurd (Home Office - Aftermath).pdf [pdf]
… later today all those residential tower blocks fitted with cladding, and to provide that information to local fire and …
Published on:
CLG00030545_Email regarding PM-chaired Grenfell Tower Recovery Taskforce of 17 June at 11_00_0.pdf [pdf]
Published on:
CLG00030545_Email_regarding_PM_chaired_Grenfell_Tower_Recovery_Taskforce_of_17_June_at_11_00.pdf [pdf]
Published on:
CLG00030545_Email regarding PM-chaired Grenfell Tower Recovery Taskforce of 17 June at 11_00.pdf [pdf]
Published on:
TMO00851600_TMO document entitled _Energy Strategy and M&E Compliance Minutes 3rd June 2014_, mentions dispute with terminated fire contractor RGE..pdf [pdf]
… problems, we could consider other solutions such as cladding. Key principles: • Energy improvements should be … problems, we could consider other solutions such as cladding. Key principles: • Energy improvements should be …
Published on: